December 22, 2021
The contractor has completed primary construction, and will be addressing deficiencies over the coming weeks. This project is warrantied for a 12 month period following completion.
November 27, 2021
The eastbound lane of Grey Road 19 will be closed between Claire Glen and Martin Grove beginning Monday, November 29 for the installation of sanitary sewer. The lane is scheduled to reopen on Wednesday, December 8.
November 17, 2021
North Rock Construction has temporarily closed one lane of Grey Road 119 (Scenic Caves Road), south of Blue Mountain Road to complete ditching work. The lane is scheduled to reopen on Friday, November 19.
November 2, 2021
Construction crews will be completing the underground work this week, with paving and restoration work to continue over the next two weeks beginning on Thursday, November 4 - weather and conditions permitting. This work will result in some temporary lane and road closures on Grey Road 19, Scenic Caves Road, Blue Mountain Road, Claire Glen, Patricia Drive and Martin Grove. During the construction period, through traffic access will be maintained via marked detours. There will also be a half-day water shutoff on Patricia Drive, Claire Glen and Blue Mountain Road the week of November 8. Impacted residents will be given notice by the contractor 48 hours before the shutoff occurs.
October 28, 2021
Construction crews are scheduled to install the sanitary mainline across Grey Road 19 on Monday, November 1 and Tuesday, November 2. During this time period, traffic will be reduced to a single lane and lights will be set up for traffic control.
October 25, 2021
The final service connections on Martin Grove and Grey Road 19 are scheduled to be made in the coming week. Construction crews will also begin excavation for the mainline sewer connection to the Windfall subdivision. There will be no service interruptions or road closures associated with this work. Restoration work will also continue throughout the project area.
October 19, 2021
The Town is taking the opportunity of this project to implement improvements in the water distribution system on Grey Road 19 east of Patricia Drive. As a result, some water shutdowns will occur over the next two weeks. Written notices will be hand delivered to affected properties.
October 15, 2021
Scenic Caves Road has reopened, and installation of the box culvert on Grey Road 19 is nearing completion. Installation of services on Patricia Drive and Martin Grove may are scheduled to continue though the weekend and to be completed the week of October 18. Work on the main line sewer south of Grey Road 19 will continue next week as well.
October 1, 2021
The contractor is scheduled to begin installation of two new sections of box culvert starting Tuesday, October 5, 2021. Road closures will be found on Grey Road 19 from the Blue Mountain Resort roundabout to Claire Glen Road, and on Scenic Caves Road from the Blue Mountain Resort roundabout to Blue Mountain Road. The installations will be happening consecutively and are expected to be completed within two weeks. Posted detour routes on Blue Mountain Road and Claire Glen Road will ensure access from all directions is maintained for public and emergency vehicles while construction takes place.
September 13, 2021
The contractor has two crews working right now working on the sanitary sewers and services. The sewer and service installation on Claire Glen is complete. The sewer and services on Patricia Drive and Blue Mountain Road are slated to be finished this week, and then the crews will be transitioning onto Martin Grove. A third crew is scheduled to be on site the week of September 20 to begin working on the storm water diversion.
August 26, 2021
Main line work has been completed on Claire Glen and a second crew has begun work to complete servicing on Claire Glen. Main line work is nearing completion on Blue Mountain Road as construction continues on Patricia Drive. After main line work is completed on Patricia Drive, the servicing crew will begin work on servicing. A third crew is set to arrive in early September to begin work on drainage improvements.
August 16, 2021
Due to construction, there may be a temporary interruption in the collection of waste and recycling. If not collected on the scheduled pick-up day, it will be collected by the end of the following day.
August 13, 2021
Construction is wrapping up on Claire Glen and crews will begin work on Blue Mountain Road between Claire Glen and Patricia Drive. There will be temporary access to County Road 19 for cars on Patricia Drive.
August 6, 2021
North Rock Construction is continuing work on Claire Glen.
July 23, 2021
Sewer construction will continue on Claire Glen for the week of July 26.
July 16, 2021
Construction is continuing on Claire Glen next week, with tree clearing to continue on Patricia Drive and Martin Grove.
July 9, 2021
North Rock Ltd. Construction will be onsite beginning July 12 to start tree clearing and sewer installation.